Given the network plan that follows, compute the early, late, and slack times. What is the… 1 answer below »

Given the network plan that follows, compute the early, late, and slack times. What is the project duration? Using any approach you wish, develop a loading chart for resources A and B. Assume only one of resource A is available and two of resource B are available. Given your resource schedule, compute the early, late, and slack times for your project. Which activities are now critical? What is the project duration now?
 